{"id":6310,"date":"2022-02-27T11:15:32","date_gmt":"2022-02-27T09:15:32","guid":{"rendered":"https:\/\/lbc.com.ly\/en\/?p=6310"},"modified":"2022-02-27T11:15:33","modified_gmt":"2022-02-27T09:15:33","slug":"three-urgently-built-power-stations-near-completion-to-be-ready-before-peak-summer-demand-aldabaiba-government","status":"publish","type":"post","link":"https:\/\/lbc.com.ly\/en\/three-urgently-built-power-stations-near-completion-to-be-ready-before-peak-summer-demand-aldabaiba-government\/","title":{"rendered":"Three urgently-built power stations near completion \u2013 to be ready before peak summer demand: Aldabaiba government"},"content":{"rendered":"\n
The current Libyan Government of National Unity (GNU), led by Caretaker Prime Minister Abd Alhamid Aldabaiba, has promised that the three \u2018\u2018urgent\u2019\u2019 power stations nearing completion will be ready before this summer\u2019s peak demand period.<\/p>\n\n\n\n
The government\u2019s information social media page put this nearing success to the \u2018\u2018efforts made by Prime Minister Abd Alhamid Aldabaiba to alleviate the electricity crisis in the country.\u2019\u2019<\/p>\n\n\n\n
Tripoli West gas power station -670 MW-completion rate 87 percent
The Tripoli West gas station project, in Tripoli, has a production capacity of 670 MW and has reached a completion rate of 87 percent. It is being implemented by Germany\u2019s Siemens and Turkey\u2019s ENCA.<\/p>\n\n\n\n
Misrata gas power station \u2013 640 MW-completion rate of 83 percent
The urgent Misrata power station project in the city of Misrata, which the government said is one of the \u2018\u2018revival of life\u2019\u2019 projects to revive development projects in the country. It has reached a completion rate of 83 percent and has a production capacity of 640 MW. It is under the supervision of the General Electricity Company, and the implementation of the Germany\u2019s Siemens and Turkey\u2019s ENCA.<\/p>\n\n\n\n
Tobruk gas power station \u2013 740 MW-completion rate 80 percent
Tobruk power station has a production capacity of 740 MW and has reached a completion rate of 80 percent. It is being implemented by Greece\u2019s Metka company. It is expected that the first of its four units will be operational before the summer peak demand.<\/p>\n\n\n\n
Analysis: Aldabaiba\u2019s trust deficit \u2013 can the Caretaker PM be believed?
it will be recalled that upon gaining office last March, Caretaker PM Aldabaiba had promised that Libya\u2019s electricity crisis would be over by year end. Later this became by November and then December. The power cuts, while much improved on the Faiez Serraj era, have persisted.<\/p>\n\n\n\n
Moreover, the Caretaker PM has a trust deficit with \u2013 to a varying degree \u2013 the Libyan public. It will be recalled that upon standing to be selected through the Geneva Libyan Political Dialogue Forum (LPDF) he had signed an undertaking not to stand for the 24 December 2021 elections. But Aldabaiba stood for the elections and brushed aside the undertaking not to stand as an ethical and not a legal undertaking.<\/p>\n\n\n\n
This has led many Libyans to take anything Aldabaiba says with a pinch of salt.<\/p>\n","protected":false},"excerpt":{"rendered":"
The current Libyan Government of National Unity (GNU), led by Caretaker Prime Minister Abd Alhamid Aldabaiba, has promised that the three \u2018\u2018urgent\u2019\u2019 power stations nearing completion will be ready before this summer\u2019s peak demand period. The government\u2019s information social media page put this nearing success to the \u2018\u2018efforts made by Prime Minister Abd Alhamid Aldabaiba […]<\/p>\n","protected":false},"author":87,"featured_media":6311,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[1],"tags":[1879],"class_list":["post-6310","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-news","tag-libyan-government"],"acf":[],"_links":{"self":[{"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/posts\/6310","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/users\/87"}],"replies":[{"embeddable":true,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/comments?post=6310"}],"version-history":[{"count":3,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/posts\/6310\/revisions"}],"predecessor-version":[{"id":6314,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/posts\/6310\/revisions\/6314"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/media\/6311"}],"wp:attachment":[{"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/media?parent=6310"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/categories?post=6310"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/lbc.com.ly\/en\/wp-json\/wp\/v2\/tags?post=6310"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}